Virgin Orbit to move ahead with U.K. Liftoff plans

Both sides of the Atlantic have encountered some liftoff problems. However, Virgin Orbit and British Authorities are working hard to commence on the flights belonging to the structure of the firm. The launching activity will take place at an English airport in the coming two years. 

On June 4 this year, the U.K. Space Agency, Virgin Orbit, and Spaceport Cornwall held a meeting that provided the way forward concerning the plans of the firm by carrying out their operations from Cornwall Airport New quay, a spaceport found on the southwest of England. A rocket by the name LuncherOne and an aircraft carrier called Boeing 747 will be the ones that will aid in the launching process. 

Cornwall Council Director, Miles Carden said that the firm anticipates attaining their launch goal come 2021 or early 2022. Cornwall Council helped in the funding of the infrastructure of the airport as well as making some adjustments by partnering with the U.K Space Agency and Virgin Orbit firms.

The main agenda for that meeting was to discuss Virgin Orbit purchasing some of the departments belonging to British Firms.  

In June, the firm will issue out its request for its proposal about a TGOS, a ground operating structure. The system consists of tanks, generators, and structures that help in the provision of fuel and preparation of LauncherOne rocket. 

Britain will be the one to manufacture the TGOS. The TGOS will be the portable form of Virgin Orbit’s structure found in California, which is enormous to be transported in the air. According to the firm’s officials, the designing of the TGOS helps it to fit into a 747 prototype of a space vehicle. It has a front-loading door and spacious room to assist in the accommodation of two LauncherOne Rocket and cargos. 

Virgin Orbit plans to pick on a top-ranked contractor for the TGOS in September, the reason being having an approved structure that will help in the launching of the LauncherOne operations in 2021. 

The progress of LauncherOne follows the first unsuccessful launch that occurred in May. The separation of the rocket from 747 was successful, so the ignition of the engine. However, the booster stage engine stopped after a few seconds into the flight, putting an end to the operation. Experts could not figure out what caused the stopping of the engine; however, with the data they have, they will be in a position to figure out the exact cause.